The short answer
In Seattle, cutting or removing a load-bearing wall always needs a building permit from the Seattle Department of Construction and Inspections (SDCI), however small the job. Most interior openings qualify for the quick subject-to-field-inspection (STFI) permit. SDCI's Tip 316, updated October 29, 2026, lets a new beam go in without an engineer's stamp when it spans no more than 8 feet under two stories and a roof, or 14 feet under one story and a roof. A longer beam, or one under three stories, needs plans stamped by a civil or structural engineer.
Key points
- 01Any work on a load-bearing wall needs a Seattle building permit, even when the job costs less than the city's $6,000 exemption.
- 02A new beam up to 8 feet long under two stories and a roof, or 14 feet under one story and a roof, can go in without an engineer on the STFI permit.
- 03Longer spans, three stories above and flitch beams need a civil or structural engineer, and the city may ask for one when a shear wall or an outside wall is opened.
- 04The load has to travel through posts to the foundation, so the work below the floor can matter as much as the beam.
- 05Asbestos and lead checks come before demolition, and the framing inspection comes before the wall is closed.
In this article (7 sections)
- 01How do I know if a wall is load-bearing?
- 02Do I need a permit to remove a load-bearing wall in Seattle?
- 03How long can a beam be without an engineer?
- 04When do you need a structural engineer?
- 05Where does the load go once the wall is gone?
- 06What happens, in order, when a load-bearing wall comes out?
- 07What else changes when the wall is in an older Seattle house?
How do I know if a wall is load-bearing?
The Seattle Residential Code defines a load-bearing wall as a wall supporting any vertical load in addition to its own weight. In a house that usually means floor joists, ceiling joists or rafters rest on top of it. Only a look at the framing confirms it, but these signs point the way:
- Joists in the floor or ceiling above run across the wall and sit on its top plate, rather than running alongside it.
- There is a wall, a beam or a row of posts directly below it in the basement or crawl space.
- There is a wall directly above it on the next floor.
- It is an outside wall. Outside walls carry the roof and floors in almost every house.
A wall can also matter without carrying weight. Shear walls brace the house against wind and earthquakes. SDCI's Tip 316 says that if you remove a shear wall, or add a window or door in an outside wall, you must show the house can still resist wind and earthquake loads, and the city may ask for plans stamped by a civil or structural engineer.
Do I need a permit to remove a load-bearing wall in Seattle?
Yes. SDCI says you need a permit for any work on load-bearing supports 'no matter how small the project'. The exemption in Seattle Residential Code R105.2 for minor alterations worth $6,000 or less in six months expressly excludes removing, reducing, altering or relocating a load-bearing support.
Most interior openings use the subject-to-field-inspection (STFI) permit: the city screens the application and the building inspector checks the code on site instead of in a full desk review. SDCI typically processes STFI permits within a few working days, and the inspector can require changes during construction.
| Situation | Permit route and engineer |
|---|---|
| Non-bearing interior wall removed, job worth $6,000 or less in six months | No building permit (SRC R105.2). Electrical, plumbing or gas changes still need their own permits |
| New beam in a bearing wall, 8 ft or less, under no more than two stories and a roof | STFI permit, no engineer's stamp |
| New beam in a bearing wall, 14 ft or less, under no more than one story and a roof | STFI permit, no engineer's stamp |
| Beam longer than those limits, or carrying three stories | STFI permit with plans stamped by a civil or structural engineer |
| Shear wall removed, or a new window or door in an outside wall | STFI permit; you must show the house still resists wind and earthquakes, and the city may ask for stamped plans |
| Flitch beam (wood and steel bolted together) | STFI permit only with an engineer's stamp |
| More than three steel beams, welded steel or shear tabs, or a cantilevered steel beam | Does not qualify for STFI; full plan review |
Source: SDCI Tip 316, updated October 29, 2026, which also allows garage door headers up to 16 ft under one story and a roof, and Seattle Residential Code R105.2. Outside Seattle, Tip 316 does not apply; each city's building department sets its own rules.
The wiring and pipes inside the wall have permits of their own: an electrical permit from SDCI and, for plumbing or gas piping, a permit from Public Health Seattle and King County. The kitchen permit guide lists which permit covers what, with the 2026 fees.
How long can a beam be without an engineer?
Tip 316 sets two limits for beams and headers in load-bearing walls of existing houses and duplexes: 8 feet under no more than two stories plus the roof, and 14 feet under no more than one story plus the roof. Past them, an engineer's stamp keeps the project on the STFI route.
- Longest beam without an engineer under two stories and a roof (Tip 316)
- 8 ft
- Longest beam without an engineer under two stories and a roof (Tip 316)
- Longest beam without an engineer under one story and a roof (Tip 316)
- 14 ft
- Longest beam without an engineer under one story and a roof (Tip 316)
- SDCI's usual processing time for an STFI permit
- A few working days
- SDCI's usual processing time for an STFI permit
Count the floors resting on the wall, then the roof. A main-floor wall under a second story and a roof is the 14 foot case. A basement bearing wall under two floors and a roof is the 8 foot case. A wall in a one-story house that carries only the ceiling and roof falls within the 14 foot limit too.
Within those limits, a beam made of dimension lumber is sized from the girder and header tables of the Seattle Residential Code (R502.5 and Tables R602.7(1) to R602.7(3)), and the inspector checks it on site.
When do you need a structural engineer?
When a project steps past what the code lets a builder size from its tables. The usual triggers in a remodel:
- A beam or header longer than 8 feet under two stories and a roof, or 14 feet under one story and a roof.
- A beam that supports three stories above it.
- A flitch beam, which SDCI accepts on the STFI route only with an engineer's stamp.
- Removing a shear wall or cutting a new opening in an outside wall, where the city may ask for stamped plans.
- Cutting or notching I-joists or other engineered lumber to fit a flush beam, which the code prohibits unless the manufacturer allows it or a registered design professional designs it (SRC R502.8.2).
- Existing joists that do not meet the code's span tables, where the inspector may require engineering during construction.
Steel needs extra care. Projects with more than three steel beams, steel beams with welding or shear tabs, or cantilevered steel beams do not qualify for STFI at all and go to full plan review, which takes longer; see permit timelines.
An engineer is also worth calling when a house has been altered before and nobody can say how the loads travel.
Where does the load go once the wall is gone?
The code requires a complete load path that carries every load from where it starts, through the structure, to the foundation (SRC R301.1). Taking out a wall gathers the load it carried onto two points: the ends of the new beam. Those points need posts, and the posts need something solid under them.
- Each end of a header sits on jack studs or approved framing hardware (SRC R602.7.5), and beam ends need at least 1 1/2 inches of bearing on wood or metal (SRC R502.6).
- Below the floor, the post load continues to a beam, a wall or a footing in the basement or crawl space. Where nothing is there, a new post and footing are part of the job.
- A flush beam sits in the ceiling plane with the joists hung from it in metal hangers, so the ceiling stays flat. A dropped beam hangs below the ceiling and is simpler to build. Either can be sized for the load; the choice is mostly about the look and the work involved.
What happens, in order, when a load-bearing wall comes out?
- 01
Check for asbestos and lead
The Puget Sound Clean Air Agency requires an asbestos survey before renovation, and in a house built before 1978, work that disturbs paint needs a lead-safe certified firm. See asbestos surveys and lead-safe renovation.
- 02
Confirm the framing and size the beam
Measure the span, count the floors and roof above, and find where the posts will land. Anything past the Tip 316 limits goes to an engineer.
- 03
Get the permits
The STFI building permit, plus electrical, plumbing or gas permits for anything rerouted. Work that needs a permit may start only once it is issued.
- 04
Reroute what runs through the wall
Wiring, pipes, vents and ducts in the wall are moved or capped by the trades under their own permits.
- 05
Shore it up
Temporary stud walls go up on one or both sides to hold the joists while the old studs come out.
- 06
Set the posts and the beam
Footings and posts first, then the beam, the hangers and the connections.
- 07
Inspect, then close up
The framing inspection is made once framing and bracing are in place and the rough wiring, plumbing and ducts are approved, before anything is covered (SRC R106.8.5). Then the ceiling, the wall ends and the strip of floor where the wall stood are patched.
What else changes when the wall is in an older Seattle house?
Two Seattle rules can widen the job. First, a building permit for an alteration brings the alarm rules with it: the house must have smoke alarms where a new house would, though battery-powered alarms are accepted in an alteration (SRC R314.2.2), and carbon monoxide alarms outside sleeping areas and on every floor are checked at inspection (SRC R315.2.2).
Second, size. Tip 316 says that if you are reconfiguring spaces or replacing wall surfaces in more than 60 percent of the house, the project is likely a substantial alteration. To stay on the STFI route, a substantial alteration needs engineer-stamped plans for seismic upgrades to the foundation and cripple walls throughout, approved Earthquake Home Retrofit plans, or proof the house was built under the 1985 Uniform Building Code or later. See bolting and bracing during a remodel, and knob-and-tube wiring for what old walls often hide.
Questions people also ask
01Can a homeowner remove a load-bearing wall in Seattle?
02How much does it cost to remove a load-bearing wall?
03Will the city inspect the new beam?
04Does a steel beam need an engineer in Seattle?
05What if a previous owner removed a wall without a permit?
Sources
- 01Seattle SDCI Tip 316: Construction and demolition subject-to-field-inspection (STFI) permits, updated Oct. 29, 2026 (read Nov 26, 2026)
- 02Seattle SDCI: Do you need a permit? (read Nov 26, 2026)
- 032021 Seattle Residential Code, chapter 1: R105.2, R106 inspections and special investigation (read Nov 26, 2026)
- 042021 Seattle Residential Code, chapter 2: definition of load-bearing wall (read Nov 26, 2026)
- 052021 Seattle Residential Code, chapter 3: R301.1 load path, R314 and R315 alarms (read Nov 26, 2026)
- 062021 Seattle Residential Code, chapter 5: R502 floor framing, bearing and notching (read Nov 26, 2026)
- 072021 Seattle Residential Code, chapter 6: R602.7 headers (read Nov 26, 2026)
- 08Seattle SDCI Tip 303A: Common Seattle Residential Code requirements (updated Dec. 8, 2021) (read Nov 26, 2026)
- 09Seattle SDCI: Electrical permit (read Nov 26, 2026)
- 10Puget Sound Clean Air Agency: asbestos rules for renovation (read Nov 26, 2026)
- 11Washington State Department of Commerce: Renovation, Repair and Painting (RRP) program (read Nov 26, 2026)
Rules, rates and programs change. This article was checked against the sources above on the dates shown. It is general information for homeowners, not legal, tax or engineering advice for a specific property.





