Permit guide · Seattle
Do you need a permit to remodel a kitchen in Seattle?
What Seattle exempts, what it does not, which of two agencies issues each permit, how long each takes and what each costs in 2026. Every rule here links to the city or county page it comes from.
By Giant Builders SeattleUpdated Rules checked against city sources in November 2026

- WA contractor license
- GIANTBS782RZ
- UBI
- 604991679
- Permits
- Prepared and filed by us
- Workmanship warranty
- 5 years
- Estimate
- Free, in your home, in writing
The short answer
Usually yes, for part of the work. Installing cabinets and new surface finishes needs no building permit in Seattle, but new wiring needs an electrical permit from the city, moved plumbing or a gas line needs a permit from Public Health, and work on a load-bearing wall or the outside walls always needs a building permit.
- Minor alterations up to this value in six months need no building permit
- $6,000
- The city's screening time for a field-inspection permit
- A few days
- Plumbing permit, plus the second figure per fixture
- $137 + $27
- How long a field-inspection permit stays valid
- 18 months
What triggers what
Which permit each part of a kitchen remodel needs
| Work | Permit | Issued by |
|---|---|---|
| Painting, installing cabinets, and new surface finishes over the existing walls and ceiling | No building permit, as long as the outside walls are not changed | Exempt under SRC R105.2 |
| Other minor repairs or alterations worth $6,000 or less in any six months | No building permit, unless a load-bearing support is touched or egress, light, ventilation or fire resistance is reduced | Exempt under SRC R105.2 |
| Replacing certain electrical equipment with the same kind, on a circuit that is not altered | No electrical permit. The Seattle Electrical Code, section 80.50, lists what counts | Seattle SDCI |
| New or changed circuits, outlets, lighting or a panel | Electrical permit | Seattle SDCI |
| Moving the sink, adding a dishwasher or pot filler line, any change to drain or supply piping | Plumbing permit | Public Health Seattle & King County |
| A new or moved gas line for a range | Gas piping permit | Public Health Seattle & King County |
| Removing a wall that carries no load, or rearranging the room, in a job over $6,000 | Construction permit, usually the subject-to-field-inspection kind | Seattle SDCI |
| Opening a load-bearing wall | Construction permit. Field-inspection route if the beam is within the span limits or is engineered | Seattle SDCI |
| A new or larger window or outside door | Construction permit: it changes the building envelope | Seattle SDCI |
| A bump-out or addition for the kitchen | Construction permit. A one-story, ground-level addition up to 750 sq ft can use the field-inspection route | Seattle SDCI |
The exemptions
What needs no building permit, and what the $6,000 rule really covers
Two lines of the Seattle Residential Code do most of the work for kitchens. They are separate exemptions, and people often blend them into one.
The named list
Section R105.2 exempts “installing kitchen cabinets, paneling or other surface finishes over existing wall and ceiling systems”, along with painting and insulating, provided no changes are made to the building envelope. There is no dollar limit on this line: new cabinets and a new backsplash can cost $40,000 and still need no building permit. Countertops and flooring are not named in it. If those are the only other work and the job is over $6,000, ask the city before you assume.
The $6,000 rule
The same section exempts other minor repairs or alterations when the value of construction is $6,000 or less in any six month period. The city counts the fair market value of labor and parts, even if you do the work yourself. The exemption never covers removing, cutting or moving a load-bearing support, and egress, light, ventilation and fire resistance may not be reduced without a permit.
What neither exemption does
Both are exemptions from the building permit only. Electrical and plumbing work have their own permits, under their own codes. And the code says all work must comply with it even where no permit is required.
A permit is always needed for
- Any work on load-bearing supports
- Changes to the building envelope: outside walls, windows, doors, roof
- Work that reduces egress, light or ventilation
- Work that reduces fire resistance
The city’s words: “no matter how small the project”.
The quick permit
How the subject-to-field-inspection permit works
Most kitchens that need a building permit qualify for this one. The city calls it the easiest type of permit to apply for. In return for skipping the desk review, the owner accepts that the inspector may ask for changes on site.
- 01
Draw the room
A floor plan of the kitchen as it is and as it will be, with the framing, the openings and any new beam, plus a location plan and the city's checklist.
- 02
Apply online
Plans go in through the Seattle Services Portal. The permit fee is paid when you apply.
- 03
Screening
The city checks that the project fits this permit and the land use code. It says this takes a few days.
- 04
Permit issued
The permit and the stamped plans arrive in the portal. Work that needs the permit may start now, not before.
- 05
Inspections
The inspector reviews the building code on site during construction and may ask for changes. The permit is valid for 18 months.
Kitchens that qualify
- Interior alterations that do not touch the structure.
- A new beam or header in a bearing wall, without an engineer, when it spans no more than 8 feet under two stories and a roof, or 14 feet under one story and a roof.
- A longer beam, or one under three stories, when a civil or structural engineer stamps the plans.
- Window and siding replacement, and a one-story addition at ground level up to 750 square feet.
If you remove a shear wall or add a window or door in an outside wall, the city may ask for an engineer’s plans showing the house still resists wind and earthquake loads.
Projects that go to full plan review
- A second-story or two-story addition.
- Outside work on a site with an environmentally critical area, unless city staff approve it.
- Anything that changes the number of homes in the building.
For those, the city tries to finish its first review of a simple application in two to three weeks and of a complex one in eight. About three quarters of the fee is due when the plans go in.
Fees
What kitchen permits cost in Seattle in 2026
| Value of the work | Field-inspection permit | Permit with full plan review |
|---|---|---|
| $25,000 | $1,042.23 | $1,488.90 |
| $50,000 | $1,611.86 | $2,302.65 |
| $90,000 | $2,471.81 | $3,531.15 |
| $150,000 | $3,247.23 | $4,638.90 |
The trade permits
- Electrical (SDCI): $55.48 administrative fee, $26.28 for each new or altered circuit up to 25 amps, $43.80 for a 30 to 50 amp circuit such as a range, with a minimum of $105.12, plus the 5% technology fee.
- Plumbing (Public Health): $137 plus $27 per fixture.
- Gas piping (Public Health): $137 plus $27 per outlet.
Rules that come with the permit
A building permit for an alteration also brings the house’s smoke alarms up to the standard for new homes, and battery alarms are accepted for this. Carbon monoxide alarms are required in existing homes and are checked at inspection. A range hood normally exhausts to the outside; the code allows a listed ductless hood only in limited cases. And when a project with demolition is worth more than $75,000 or covers more than 750 square feet, the city asks for a salvage assessment up front and a waste diversion report within 60 days of the final inspection.
Before demolition in any house, the Puget Sound Clean Air Agency requires an asbestos survey, with a copy kept on site. In a house built before 1978, Washington's lead rules, run by the Department of Commerce, require a certified firm and lead-safe work practices.
A worked example
The permits on one kitchen, added up
Worked example, not a real job
Example: a kitchen opened to the dining room, with an island sink and a gas range
A typical reconfigured kitchen valued at $150,000, where the usual Seattle range for a kitchen that moves walls begins. The bearing wall is replaced by a 12 foot beam under one story and a roof, inside the city's 14 foot limit, so the job still uses the field-inspection permit. Every fee is computed from the 2026 schedules.
| Line | How it is worked out | Amount |
|---|---|---|
| Construction contract | The example figure the fees are based on. | $150,000 |
| Sales tax | 10.55% of the contract price (Seattle, October to December 2026). | $15,825 |
| Building permit (SDCI) | Permit fee $2,209, plan review fee $883.60, technology fee $154.63. | $3,247.23 |
| Electrical permit (SDCI) | $55.48 administrative fee, 10 circuits up to 25 amps, one range circuit, plus 5%. | $380.18 |
| Plumbing permit (Public Health) | $137 plus $27 for each of 4 fixtures. | $245 |
| Gas piping permit (Public Health) | $137 plus $27 for one outlet. | $164 |
| Total with tax and permits | $169,861.41 | |
Get the permit list for your project
The permit navigator asks what you are changing and where you live, and returns the permits that apply, for Seattle and for the cities around it.
Questions
Kitchen permit questions, answered
01Do I need a permit to remodel my kitchen in Seattle?
For most real remodels, yes, for part of the work. Seattle's residential code exempts installing kitchen cabinets and new surface finishes over existing walls, and minor alterations worth $6,000 or less in six months. New or changed wiring still needs an electrical permit from the city, a moved sink or a new gas line needs a permit from Public Health Seattle & King County, and any work on a load-bearing wall or on the outside walls needs a building permit, whatever it costs.
02Do I need a permit to replace kitchen cabinets or countertops in Seattle?
No building permit. Seattle Residential Code section R105.2 lists installing kitchen cabinets and surface finishes over existing wall and ceiling systems as work exempt from a building permit, as long as the building envelope is not changed. Countertops are not named in that list; replacing them touches no structure, and the city can confirm for your project. If the new layout moves the sink, adds outlets or needs a new circuit for an appliance, those parts need plumbing and electrical permits.
03What is a subject-to-field-inspection permit?
It is Seattle's quicker building permit for small projects, often written STFI. The city screens the plans in a few days and does not do a full code review at the desk. The inspector checks the work against the code on site. Kitchens qualify when the changes are interior and any new beam or header stays within the city's span limits, or is designed and stamped by an engineer.
04How long does a kitchen permit take in Seattle?
Electrical permits that need no plan review are issued the same day online. The city says screening a subject-to-field-inspection building permit takes a few days. A project that needs full plan review waits longer: the city tries to finish its first review of a simple application in two to three weeks and of a complex one in eight, and corrections add to that.
05How much does a kitchen remodel permit cost in Seattle?
The building permit fee follows the value of the work. On the field-inspection route the 2026 schedule comes to $1,611.86 for $50,000 of work and $2,471.81 for $90,000, with the technology fee. The electrical permit is $55.48 plus $26.28 for each circuit up to 25 amps, and a plumbing or gas permit from Public Health is $137 plus $27 per fixture or outlet. In the worked example on this page the four permits come to $4,036.41, about 2.7% of a $150,000 job.
06Can a homeowner pull kitchen permits in Seattle?
Yes. The city says house drawings rarely need an architect's or engineer's stamp and that you may prepare them yourself. Property owners may do their own electrical work in a home they own and live in, and a plumbing permit issued to a homeowner authorizes the homeowner to do the plumbing. A hired electrician must hold a state electrical contractor license and applies for the electrical permit, and a hired plumber must be a registered contractor. When we are the contractor, we prepare and file the permits.
07What happens if a kitchen is remodeled without a permit?
The work still has to meet the code, and it can surface later: the city lists resale value, insurance coverage for repairs and complaints about unpermitted work as reasons to get the permit. Its fee schedule also has a special investigation fee, which the city can add to the permit fee when it has to investigate work that needed its approval: three times the base fee, or $876, for work valued from $5,001 to $50,000, and five times, or $1,460, from $50,001 to $100,000.
Outside Seattle? See the local remodel guides for the permit office in Bellevue, Kirkland, Redmond and seven more cities. Each city has its own exemptions and fees, and outside Seattle the city itself issues the plumbing permit.
Free estimate
We prepare and file the permits
Tell us what you want to change. We work out which permits apply, draw what the city needs and file them, as part of the job.
Washington general contractor GIANTBS782RZ, registered with the Department of Labor & Industries. The record is public.
Keep reading
- Kitchen remodelingWhat is included and how a kitchen remodel runs.
- Kitchen remodel cost in SeattleRanges by scope and size, with tax and permits added.
- Bathroom remodel permits in SeattleThe same rules applied to a bathroom.
- Basement finishing permits in SeattleCeiling height, escape windows and the permit route.
Sources
- 01Seattle SDCI: Do you need a permit? (read Nov 18, 2026)
- 022021 Seattle Residential Code, chapter 1: section R105.2, work exempt from permit (read Nov 18, 2026)
- 03Seattle SDCI: House additions and remodels (read Nov 18, 2026)
- 04Seattle SDCI: Construction permit, subject to field inspection (read Nov 18, 2026)
- 05Seattle SDCI: Subject-to-field-inspection criteria, infographic (read Nov 18, 2026)
- 06Seattle SDCI Tip 316: Subject-to-field-inspection permits (updated Oct. 29, 2026) (read Nov 18, 2026)
- 07Seattle SDCI: Construction permit, addition or alteration (read Nov 18, 2026)
- 08Seattle SDCI: 2026 Fee Subtitle (effective Jan. 1, 2026) (read Nov 18, 2026)
- 09Seattle SDCI: How much will your permit cost? (read Nov 18, 2026)
- 10Seattle SDCI: Electrical permit (read Nov 18, 2026)
- 11Seattle SDCI Tip 104: Getting an over-the-counter permit (dated July 25, 2022) (read Nov 18, 2026)
- 12Public Health Seattle & King County: plumbing and gas piping permits (read Nov 18, 2026)
- 13Public Health Seattle & King County: plumbing and gas piping fees (effective Jan. 1, 2026) (read Nov 18, 2026)
- 142021 Seattle Residential Code, chapter 3: sections R303 to R315 (light, room size, ceiling height, escape openings, alarms) (read Nov 18, 2026)
- 15Seattle SDCI Tip 303A: Common Seattle Residential Code requirements (dated Dec. 8, 2021) (read Nov 18, 2026)
- 16Puget Sound Clean Air Agency: asbestos rules for renovation (read Nov 18, 2026)
- 17U.S. EPA: Lead Renovation, Repair and Painting program (read Nov 18, 2026)
- 18Washington Dept. of Revenue: local sales tax rates, October to December 2026 (read Nov 18, 2026)