The short answer
In Seattle, a small remodel that qualifies for a subject-to-field-inspection permit is usually processed within a few working days, and many electrical permits are issued the same day online. A remodel that needs full plan review takes longer: SDCI aims to finish the first review of a simple application in 2 to 3 weeks and a complex one in 8. Bellevue's target for a first review of a single-family remodel is 14 days, Kirkland's runs from 3 business days to 4 weeks by review track, and Redmond publishes no target.
Key points
- 01Seattle's subject-to-field-inspection permit is processed in a few working days, while full plan review starts with a first review of 2 to 3 weeks for a simple project and about 8 for a complex one.
- 02Seattle's goal since October 1, 2025 is 30 days in city hands for a single-family addition or alteration; on November 26, 2026 its own dashboard showed 64 days at the 75th percentile.
- 03Bellevue, Kirkland and Mercer Island publish review targets in days or weeks; Redmond publishes none for a house remodel.
- 04Targets count the city's time only. Each round of corrections adds the applicant's time plus another review.
In this article (8 sections)
- 01How long does a remodel permit take in Seattle?
- 02What does Seattle's permit dashboard show?
- 03Which Seattle remodels qualify for the quick permit?
- 04How long do Bellevue, Kirkland and Mercer Island take to review a remodel?
- 05Which cities publish no review target?
- 06Why do permits take longer than the city's target?
- 07Does Washington law set a deadline for permit decisions?
- 08How should you plan a start date around the permit?
How long does a remodel permit take in Seattle?
It depends on which of two permit routes the project takes. The Seattle Department of Construction and Inspections (SDCI) says it typically processes a subject-to-field-inspection (STFI) permit within a few working days of filing. An STFI permit is Seattle's quick building permit for small projects: the city screens the plans, issues the permit, and the inspector checks the code on site instead of at a desk. Projects that do not qualify go through full plan review, which takes weeks.
- SDCI's processing time for an STFI permit
- A few working days
- SDCI's processing time for an STFI permit
- SDCI's aim for the first review of a simple application with plans
- 2 to 3 weeks
- SDCI's aim for the first review of a simple application with plans
- SDCI's aim for the first review of a complex application
- 8 weeks
- SDCI's aim for the first review of a complex application
- How long an STFI permit stays valid after it is issued
- 18 months
- How long an STFI permit stays valid after it is issued
Full plan review starts with intake: SDCI says it can usually take in an application within 2 to 3 weeks of a complete upload, and about 75 percent of the fee is due then. Its help center, updated July 22, 2026, puts the target range for the first review at 2 to 4 weeks for simple and medium projects and 8 to 12 weeks for complex ones.
Trade permits run on their own track. SDCI says it issues many electrical permits on the same day the application is made online; an electrical permit that needs plan review can take up to a few weeks. Plumbing and gas permits in Seattle come from Public Health Seattle and King County, not from SDCI. The kitchen permit guide shows which part of a typical remodel needs which permit.
What does Seattle's permit dashboard show?
Since October 1, 2025, Seattle has set goals for how quickly permits move from intake to issue, counted in calendar days while the application is in city hands. SDCI publishes the goal and the current figure side by side, measured at the 75th percentile: three permits in four take less time than that figure. The table shows the categories a homeowner is most likely to fall into, as the dashboard read on November 26, 2026.
| Project category | City goal | Current, 75th percentile |
|---|---|---|
| Single-family addition or alteration (beyond what an STFI permit covers) | 30 days | 64 days |
| Middle housing (includes a house with an attached or detached ADU) | 60 days | 117 days |
| Backyard cottage built from a pre-approved DADU plan | 30 days | 60 days |
Source: SDCI, Construction Permit Performance, read November 26, 2026. The figures change as the city updates the page.
The city adds a caution that matters for planning: the total number of calendar days an applicant experiences is roughly twice the days in city control, because the days spent answering corrections and paying fees are not counted in the goal. A remodel at the 64 day figure is therefore closer to four months from intake to permit in total. SDCI's accessory dwelling unit page also says a permit with one of its pre-approved DADU plans is issued in 2 to 6 weeks in most cases; the Seattle ADU rules guide covers that route.
Which Seattle remodels qualify for the quick permit?
SDCI's Tip 316, updated October 29, 2026, lists what qualifies. The route decides more of your timeline than anything else, so it is worth knowing before the design is fixed.
- Interior alterations to a house, including new beams or headers in a bearing wall up to 8 feet long under two stories and a roof, or 14 feet under one story and a roof, without an engineer. Longer spans qualify with an engineer's stamp.
- A ground-level, one-story addition or detached accessory structure up to 750 square feet.
- A dormer up to 14 feet wide that adds no more than 200 square feet, set into the existing roof, with framing stamped by an engineer.
- Window and siding replacement, as long as new windows meet the Seattle Energy Code's prescriptive requirements.
The same Tip lists what sends a project to full plan review. For a house, the common ones are a second-story addition, turning an unheated attic into living space, lowering a basement floor, creating an ADU or DADU, harming or removing a Tier 1, 2 or 3 tree, more than 750 square feet of new and replaced hard surface, outside work on a site with an environmentally critical area such as a steep slope unless SDCI staff approve it, and an addition that does not meet the prescriptive energy code. The tree rules article and the energy code article explain those two.
How long do Bellevue, Kirkland and Mercer Island take to review a remodel?
All three publish targets, and all three say actual times vary. Bellevue, Kirkland and Mercer Island take applications through MyBuildingPermit.com, a portal shared by 14 cities and counties in the region, but each city sets its own targets.
| City | Permit or review track | First review | Each later review |
|---|---|---|---|
| Bellevue | Remodel with no plan review (over the counter) | Typically within one day | No separate figure |
| Bellevue | Single-family remodel or addition with plan review | 14 days | 10 days |
| Bellevue | New single-family house | 21 days | 14 days |
| Kirkland | Over the counter (no plan review) | Typically within one day | No separate figure |
| Kirkland | Express, single-family addition or alteration | 3 business days | 3 business days |
| Kirkland | Fast Track, single-family addition or alteration | 10 business days | 5 business days |
| Kirkland | Regular, single-family addition or alteration | 4 weeks | 10 business days |
| Mercer Island | Subject-to-field-inspection permit | 3 days | No separate figure |
| Mercer Island | Non-major building permit | 2 weeks | 2 weeks |
| Mercer Island | Major building permit | 4 weeks | 2 weeks |
Sources: City of Bellevue, permit review timelines; City of Kirkland, Time to Review Goals (last updated September 15, 2026) and Permit Review Times; City of Mercer Island, Review Timelines. All read November 26, 2026. Each city calls these targets or estimates.
Kirkland's faster tracks have limits: Fast Track takes an addition no more than half the existing square footage, and Express an addition of 500 square feet or less with no heated space and no change to the roof line. Mercer Island targets 2 weeks for intake screening and 1 week for routing before review starts, and it requires public notice with a 30 day comment period for some permits, including residential building permits; review cannot finish before the comment period ends.
Which cities publish no review target?
Redmond's permit pages give no review time for a house remodel. What the city does state is that after a request for plan review through its online portal, it emails a permit number and instructions within 48 hours, and that a permit stays valid for 365 days without an inspection, with each passed inspection extending it another 365 days. For a Redmond remodel with drawings, ask the Development Services Center for its current estimate when you apply, and do not set a start date from another city's figure.
Elsewhere, check the city's own page before you rely on a number. The local remodel guides list the permit office, how to apply and what each city publishes about review times.
Why do permits take longer than the city's target?
A target covers one review by the city. Most permits with plans go through several rounds, and the clock behaves differently in each.
- 01
Intake
The city checks that the application is complete. In Seattle this usually happens within 2 to 3 weeks of a complete upload; Mercer Island targets 2 weeks once all documents are in.
- 02
First review
Each reviewer (building, zoning, drainage, trees, energy) reviews the plans against the target for that review type.
- 03
Correction notice
The city sends comments. The clock on the city's target stops while the designer revises the plans.
- 04
Resubmittal and re-review
The revised plans go back for another review, with its own target: 10 days in Bellevue, 2 weeks on Mercer Island, 3 to 10 business days in Kirkland.
- 05
Issue
Once every review is approved and the fees are paid, the permit is issued. Work that needs the permit may start only then.
Incomplete drawings, missing engineering such as beam calculations, and slow answers to comments all add rounds or applicant days, which is why Seattle's total time runs about twice its city time. SDCI also notes that STFI processing varies with seasonal demand.
Does Washington law set a deadline for permit decisions?
Not for a building permit. Washington's local project review law, RCW 36.70B.080, sets deadlines for a final decision on a project permit: 65 days after the application is found complete when no public notice is required, 100 days with public notice, and 170 days with notice and a hearing, with fee refunds when a city misses them. But as the definitions in RCW 36.70B.020 read today, a project permit does not include permits issued based on compliance with state and local building codes. Those deadlines apply to land use approvals, not to the building permit for a remodel.
One part of the same law does help a remodel. Under RCW 36.70B.140, a city must exclude interior alterations from site plan review, provided they add no sleeping rooms and do not trigger flood or fire access upgrades. The building, plumbing, mechanical and electrical codes still apply.
How should you plan a start date around the permit?
Work backward from the route the project will take, and treat the published target as the shortest likely wait, not the expected one.
- Decide early whether the design fits the quick route. In Seattle that means checking spans, tree locations, hard surface and the energy code before the drawings are final.
- Order engineering and any soils or tree report before the application, not after the first correction notice.
- Book the asbestos survey before demolition; the asbestos article explains why it comes first.
- Expect at least one round of corrections on any permit with plan review, and budget the time for it.
- Order long-lead items such as windows and cabinets once the permit route is clear, so they do not arrive months before the work can start.
- Read the city's own review page on the day you apply. Targets and dashboards change.
For a list of the permits your project needs in Seattle or the cities around it, use the permit navigator. When we build a project, we prepare and file the permits as part of the job.
Questions people also ask
01Can I pick up a building permit in person in Seattle?
02How long is a Seattle STFI permit valid?
03Do electrical and plumbing permits wait for the building permit?
04Does a pre-approved backyard cottage plan get a faster permit in Seattle?
Sources
- 01Seattle SDCI: Construction permit, addition or alteration (review and intake times) (read Nov 26, 2026)
- 02Seattle SDCI: Construction permit, subject to field inspection (read Nov 26, 2026)
- 03Seattle SDCI Tip 316: Subject-to-field-inspection permits (updated Oct. 29, 2026) (read Nov 26, 2026)
- 04Seattle SDCI: Construction Permit Performance (goals and current figures) (read Nov 26, 2026)
- 05Seattle Services Portal help center: SDCI review status and target due dates (updated July 22, 2026) (read Nov 26, 2026)
- 06Seattle SDCI: Electrical permit (read Nov 26, 2026)
- 07Seattle SDCI: 2026 Fee Subtitle, Table B-2 special investigation fees (effective Jan. 1, 2026) (read Nov 26, 2026)
- 08Seattle SDCI: Accessory dwelling units (pre-approved DADU plans) (read Nov 26, 2026)
- 09Public Health Seattle and King County: plumbing and gas piping permits (read Nov 26, 2026)
- 10City of Bellevue: Permit review timelines (read Nov 26, 2026)
- 11City of Kirkland: Permit review times (read Nov 26, 2026)
- 12City of Kirkland: Time to Review Goals (last updated Sept. 15, 2026) (read Nov 26, 2026)
- 13City of Mercer Island: Review timelines (read Nov 26, 2026)
- 14City of Redmond: How to apply for a permit (read Nov 26, 2026)
- 15City of Redmond: Residential permits (read Nov 26, 2026)
- 16MyBuildingPermit.com: participating jurisdictions (read Nov 26, 2026)
- 17RCW 36.70B.080: time periods for project permit decisions (read Nov 26, 2026)
- 18RCW 36.70B.020: definition of project permit (read Nov 26, 2026)
- 19RCW 36.70B.140: exclusions, including interior alterations from site plan review (read Nov 26, 2026)
Rules, rates and programs change. This article was checked against the sources above on the dates shown. It is general information for homeowners, not legal, tax or engineering advice for a specific property.