How long does a remodel permit take in Seattle?

It depends on which of two permit routes the project takes. The Seattle Department of Construction and Inspections (SDCI) says it typically processes a subject-to-field-inspection (STFI) permit within a few working days of filing. An STFI permit is Seattle's quick building permit for small projects: the city screens the plans, issues the permit, and the inspector checks the code on site instead of at a desk. Projects that do not qualify go through full plan review, which takes weeks.

SDCI's processing time for an STFI permit
A few working days
SDCI's processing time for an STFI permit
SDCI's aim for the first review of a simple application with plans
2 to 3 weeks
SDCI's aim for the first review of a simple application with plans
SDCI's aim for the first review of a complex application
8 weeks
SDCI's aim for the first review of a complex application
How long an STFI permit stays valid after it is issued
18 months
How long an STFI permit stays valid after it is issued

Full plan review starts with intake: SDCI says it can usually take in an application within 2 to 3 weeks of a complete upload, and about 75 percent of the fee is due then. Its help center, updated July 22, 2026, puts the target range for the first review at 2 to 4 weeks for simple and medium projects and 8 to 12 weeks for complex ones.

Trade permits run on their own track. SDCI says it issues many electrical permits on the same day the application is made online; an electrical permit that needs plan review can take up to a few weeks. Plumbing and gas permits in Seattle come from Public Health Seattle and King County, not from SDCI. The kitchen permit guide shows which part of a typical remodel needs which permit.

What does Seattle's permit dashboard show?

Since October 1, 2025, Seattle has set goals for how quickly permits move from intake to issue, counted in calendar days while the application is in city hands. SDCI publishes the goal and the current figure side by side, measured at the 75th percentile: three permits in four take less time than that figure. The table shows the categories a homeowner is most likely to fall into, as the dashboard read on November 26, 2026.

Seattle construction permits: calendar days in city control, intake to issue
Project categoryCity goalCurrent, 75th percentile
Single-family addition or alteration (beyond what an STFI permit covers)30 days64 days
Middle housing (includes a house with an attached or detached ADU)60 days117 days
Backyard cottage built from a pre-approved DADU plan30 days60 days

Source: SDCI, Construction Permit Performance, read November 26, 2026. The figures change as the city updates the page.

The city adds a caution that matters for planning: the total number of calendar days an applicant experiences is roughly twice the days in city control, because the days spent answering corrections and paying fees are not counted in the goal. A remodel at the 64 day figure is therefore closer to four months from intake to permit in total. SDCI's accessory dwelling unit page also says a permit with one of its pre-approved DADU plans is issued in 2 to 6 weeks in most cases; the Seattle ADU rules guide covers that route.

Which Seattle remodels qualify for the quick permit?

SDCI's Tip 316, updated October 29, 2026, lists what qualifies. The route decides more of your timeline than anything else, so it is worth knowing before the design is fixed.

  • Interior alterations to a house, including new beams or headers in a bearing wall up to 8 feet long under two stories and a roof, or 14 feet under one story and a roof, without an engineer. Longer spans qualify with an engineer's stamp.
  • A ground-level, one-story addition or detached accessory structure up to 750 square feet.
  • A dormer up to 14 feet wide that adds no more than 200 square feet, set into the existing roof, with framing stamped by an engineer.
  • Window and siding replacement, as long as new windows meet the Seattle Energy Code's prescriptive requirements.

The same Tip lists what sends a project to full plan review. For a house, the common ones are a second-story addition, turning an unheated attic into living space, lowering a basement floor, creating an ADU or DADU, harming or removing a Tier 1, 2 or 3 tree, more than 750 square feet of new and replaced hard surface, outside work on a site with an environmentally critical area such as a steep slope unless SDCI staff approve it, and an addition that does not meet the prescriptive energy code. The tree rules article and the energy code article explain those two.

How long do Bellevue, Kirkland and Mercer Island take to review a remodel?

All three publish targets, and all three say actual times vary. Bellevue, Kirkland and Mercer Island take applications through MyBuildingPermit.com, a portal shared by 14 cities and counties in the region, but each city sets its own targets.

Published review targets for house remodels and additions
CityPermit or review trackFirst reviewEach later review
BellevueRemodel with no plan review (over the counter)Typically within one dayNo separate figure
BellevueSingle-family remodel or addition with plan review14 days10 days
BellevueNew single-family house21 days14 days
KirklandOver the counter (no plan review)Typically within one dayNo separate figure
KirklandExpress, single-family addition or alteration3 business days3 business days
KirklandFast Track, single-family addition or alteration10 business days5 business days
KirklandRegular, single-family addition or alteration4 weeks10 business days
Mercer IslandSubject-to-field-inspection permit3 daysNo separate figure
Mercer IslandNon-major building permit2 weeks2 weeks
Mercer IslandMajor building permit4 weeks2 weeks

Sources: City of Bellevue, permit review timelines; City of Kirkland, Time to Review Goals (last updated September 15, 2026) and Permit Review Times; City of Mercer Island, Review Timelines. All read November 26, 2026. Each city calls these targets or estimates.

Kirkland's faster tracks have limits: Fast Track takes an addition no more than half the existing square footage, and Express an addition of 500 square feet or less with no heated space and no change to the roof line. Mercer Island targets 2 weeks for intake screening and 1 week for routing before review starts, and it requires public notice with a 30 day comment period for some permits, including residential building permits; review cannot finish before the comment period ends.

Which cities publish no review target?

Redmond's permit pages give no review time for a house remodel. What the city does state is that after a request for plan review through its online portal, it emails a permit number and instructions within 48 hours, and that a permit stays valid for 365 days without an inspection, with each passed inspection extending it another 365 days. For a Redmond remodel with drawings, ask the Development Services Center for its current estimate when you apply, and do not set a start date from another city's figure.

Elsewhere, check the city's own page before you rely on a number. The local remodel guides list the permit office, how to apply and what each city publishes about review times.

Why do permits take longer than the city's target?

A target covers one review by the city. Most permits with plans go through several rounds, and the clock behaves differently in each.

  1. 01

    Intake

    The city checks that the application is complete. In Seattle this usually happens within 2 to 3 weeks of a complete upload; Mercer Island targets 2 weeks once all documents are in.

  2. 02

    First review

    Each reviewer (building, zoning, drainage, trees, energy) reviews the plans against the target for that review type.

  3. 03

    Correction notice

    The city sends comments. The clock on the city's target stops while the designer revises the plans.

  4. 04

    Resubmittal and re-review

    The revised plans go back for another review, with its own target: 10 days in Bellevue, 2 weeks on Mercer Island, 3 to 10 business days in Kirkland.

  5. 05

    Issue

    Once every review is approved and the fees are paid, the permit is issued. Work that needs the permit may start only then.

Incomplete drawings, missing engineering such as beam calculations, and slow answers to comments all add rounds or applicant days, which is why Seattle's total time runs about twice its city time. SDCI also notes that STFI processing varies with seasonal demand.

Does Washington law set a deadline for permit decisions?

Not for a building permit. Washington's local project review law, RCW 36.70B.080, sets deadlines for a final decision on a project permit: 65 days after the application is found complete when no public notice is required, 100 days with public notice, and 170 days with notice and a hearing, with fee refunds when a city misses them. But as the definitions in RCW 36.70B.020 read today, a project permit does not include permits issued based on compliance with state and local building codes. Those deadlines apply to land use approvals, not to the building permit for a remodel.

One part of the same law does help a remodel. Under RCW 36.70B.140, a city must exclude interior alterations from site plan review, provided they add no sleeping rooms and do not trigger flood or fire access upgrades. The building, plumbing, mechanical and electrical codes still apply.

How should you plan a start date around the permit?

Work backward from the route the project will take, and treat the published target as the shortest likely wait, not the expected one.

  • Decide early whether the design fits the quick route. In Seattle that means checking spans, tree locations, hard surface and the energy code before the drawings are final.
  • Order engineering and any soils or tree report before the application, not after the first correction notice.
  • Book the asbestos survey before demolition; the asbestos article explains why it comes first.
  • Expect at least one round of corrections on any permit with plan review, and budget the time for it.
  • Order long-lead items such as windows and cabinets once the permit route is clear, so they do not arrive months before the work can start.
  • Read the city's own review page on the day you apply. Targets and dashboards change.