How long does a kitchen remodel take from start to finish?

It depends on how much of the room changes. The ranges below are the typical time on site used in the kitchen cost guide. They are planning figures for Seattle-area houses, not a promise for one kitchen.

Typical time on site by scope
ScopeWhat changesTypical time on site
RefreshThe layout stays. New counters, backsplash, sink, faucet and lighting; cabinets refaced, painted or partly replaced3 to 6 weeks
Full remodelBack to the studs. All new cabinets, counters and flooring, new wiring and plumbing, appliances or the sink moved within the room8 to 12 weeks
ReconfigureWalls move. A bearing wall is opened with a beam, the kitchen grows into the next room, or new windows and doors are cut12 to 20 weeks

Typical ranges, not a quote or a schedule. A written schedule comes with the contract.

Before any of that, design, selections and permits usually take 4 to 10 weeks. Special-order cabinets and appliances can set the start date more than any permit, so the order date matters as much as the permit date.

What happens before demolition starts?

  1. 01

    Visit, measure and look behind the walls

    Measure the room and check the panel, the plumbing under the sink and in the basement, which walls carry load, and where the hood vents today. What is found here is what keeps surprises out of the schedule.

  2. 02

    Design and selections

    Layout, cabinet drawings, appliances, counters, tile, fixtures and lighting are chosen and written into the estimate. Every choice made now is one that cannot hold up the crew later.

  3. 03

    Order long-lead items

    Cabinets, appliances and special-order fixtures are ordered once the selections are final. Get each lead time in writing and plan demolition around the longest one.

  4. 04

    Surveys for older houses

    The Puget Sound Clean Air Agency requires an asbestos survey before renovation. If asbestos will be removed, a notification and fee go to the agency first, and a waiting period of up to 10 days may apply depending on the size of the job. In a house built before 1978, work that disturbs paint needs a lead-safe certified firm.

  5. 05

    Permits

    Electrical permits without plan review are often issued online the same day. A building permit for a kitchen that moves walls is usually the subject-to-field-inspection (STFI) kind, which SDCI typically processes within a few working days. Plumbing and gas permits come from Public Health Seattle and King County. Work that needs a permit may not start until it is issued.

Seattle adds one more step for bigger jobs. Under SDCI's Tip 316, a project with some demolition that is worth more than $75,000 or covers more than 750 square feet needs a salvage assessment, and a waste diversion report goes to Seattle Public Utilities within 60 days of the final inspection.

Which permits a kitchen needs, and what each costs in 2026, is in the kitchen permit guide. A project that needs full plan review takes longer; see permit timelines in Seattle and the Eastside.

What is the order of work on site?

A full kitchen remodel, stage by stage
StageWhat happensInspection before moving on
Protection and demolitionFloors and the path through the house covered, dust walls up, the old kitchen removed, down to the studs where neededNone, but the asbestos survey must be kept on site
FramingWalls moved, openings and beams built, blocking added for cabinets and the hoodFraming is inspected before it is insulated or covered
Rough-inNew circuits and boxes, supply and drain lines, gas capped or moved, the hood duct runElectrical cover inspection (SDCI) and plumbing and gas inspections (Public Health)
InsulationOpened outside-wall cavities filled: at least R-15 in 2x4 walls and R-21 in 2x6 walls under Seattle's energy codeInsulation inspection before drywall
DrywallWalls and ceiling closed, taped and primedNone
CabinetsSet, leveled and fastenedNone
CountersTemplated from the installed cabinets, fabricated, then installedNone
FinishesBacksplash tile, flooring if not laid earlier, trim and paintNone
Fixtures and appliancesSink, faucet, dishwasher, range, hood, lights and devicesElectrical, plumbing and building finals

Inspection points from the 2021 Seattle Residential Code R106.8, SDCI's construction and electrical inspection pages, and the Seattle Energy Code R503.1.1. Some kitchens lay the flooring before the cabinets.

Two rules fix this order. Seattle's residential code says work requiring inspection must stay exposed until it is approved, and no work may go past an inspection point without approval (SRC R106.4 and R106.6). SDCI's electrical inspectors want every new circuit wired, boxes installed and grounds made up before the cover inspection, and nothing covered with insulation, receptacles or switches until it passes.

How much time do inspections add?

At least the wait for the next opening at each stage, and more if the work is not ready. SDCI's service goal for electrical inspections is next-day, with limited same-day, and it warns that the next opening may be several days out. For construction inspections, a request on its 24-hour line before 7 a.m. is usually inspected the same day, and a later call is scheduled for the following workday. Public Health tells permit holders to plan for several business days after requesting a plumbing or gas inspection.

SDCI's service goal for electrical inspections
Next day
SDCI's service goal for electrical inspections
Public Health's planning time for plumbing and gas inspections
Several business days
Public Health's planning time for plumbing and gas inspections
How long a Seattle permit stays valid after it is issued
18 months
How long a Seattle permit stays valid after it is issued

A failed inspection costs time and money. SDCI may charge a reinspection fee, and Public Health's 2026 fee for a re-inspection is $137. The cure is to call for an inspection only when a stage is complete.

Why are there days when no one is working?

Most quiet days on a kitchen job are waiting for something that cannot be rushed:

  • Counters. The fabricator measures the installed cabinets, so the counter cannot be cut until the cabinets are set and fastened.
  • Inspections. Each one has to pass before the next stage can cover it.
  • Drying and curing. Drywall compound, tile setting materials and grout each need time before the next coat or step, by the maker's instructions.
  • Deliveries. A back-ordered or damaged item stops the step that needs it, which is why deliveries are checked when they arrive, not on install day.
  • Decisions. A tile or fixture not chosen by the time it is needed stops the crew.

What usually delays a kitchen remodel, and how do you avoid it?

Three things more than any other: what is found behind the walls, changes after work starts, and late materials. Each can be planned for:

  • Finish every selection, down to the cabinet hardware, before demolition.
  • Get the lead times for cabinets, appliances and counters in writing.
  • Ask what the first visit found about wiring, pipes and framing, and how the estimate handles surprises.
  • Agree on how a change is priced and approved before work starts; see change orders.
  • Plan the temporary kitchen and the dust path for the whole job; see living through a remodel.

What happens at the end of a kitchen remodel?

The finals come last. The electrical final is made when all equipment is installed, grounded and energized and every circuit is labeled in the panel. Then the plumbing final, and the building final after every related permit has had its final. A building permit for an alteration also brings the alarm rules: smoke alarms where a new house would have them, with battery alarms accepted in an alteration, and carbon monoxide alarms outside sleeping areas and on every floor.

Then the walkthrough: you and the contractor go through the room with a list, and the job is done when the list is. Keep the permit records, appliance manuals and warranty papers together. SDCI names resale value and insurance coverage among the reasons to permit the work, and the records are the proof.