What is the difference between design-build and hiring an architect first?

The difference is how many contracts you sign and when the builder joins the project. Washington's Department of Enterprise Services, which manages the state's own construction, defines design-bid-build as a method in which the owner "contracts with separate entities for the design and construction of a project," and design-build as one in which design and construction services "are contracted by a single entity." Those definitions are written for public buildings, but a house remodel follows the same two patterns.

In a design-build remodel you hire one firm. It measures the house, works out the design with you, prices it as the design develops, prepares the permit drawings and builds the project. If the firm uses an outside architect or engineer, that person works for the firm, not for you.

In an architect-first remodel (the traditional design-bid-build path) you hire an architect or a residential designer first. They draw the project to the level of detail you agree on. You then ask several contractors to bid on the same drawings, choose one and sign a separate construction contract.

The two paths side by side
QuestionDesign-buildArchitect first
Contracts you signOne firm (sometimes a design agreement, then a construction contract)Two: the designer, then the contractor
When you see a construction priceWhile the design is being drawnAfter the drawings are finished and the bids come in
How you compare buildersOn process, early pricing and referencesOn bids for identical drawings
Who answers when drawings and house disagreeThe same firmArchitect and contractor sort it out; the fix may be a change order
ScheduleDesign, pricing and ordering overlapDesign, bidding and building run one after another
Where it can cost youLess direct price competition on the final designA design can come in over budget and need redrawing

How does a design-build remodel work?

One firm takes the project from the first visit to the final walkthrough. A typical order:

  1. 01

    First visit

    The firm walks and measures the house, looks at the structure and systems, and hears what you want.

  2. 02

    Design and pricing together

    Layouts and selections are drawn and priced in rounds, so you see what each choice costs. Some firms charge for this stage under a design agreement.

  3. 03

    Engineering and permit drawings

    The firm prepares the permit drawings and brings in a structural engineer where needed.

  4. 04

    Construction contract

    You sign a contract for the finished design, with the price, the payment schedule, the change order process and the state's disclosure statement.

  5. 05

    Build and close out

    The same firm builds it, schedules the inspections and walks the finished work with you.

The strength is that the person pricing the job sees the design as it forms, which helps keep it inside the budget in an older house where hidden conditions drive cost. The Department of Enterprise Services says design-build is used to "reduce the delivery schedule by overlapping the design phase and construction phase."

The weakness is that builders do not compete on the same finished plans. You choose the firm before the design exists, so check it carefully first.

How does the architect-first path work?

You hire the designer, the designer draws the project, and the drawings go out to bid. The usual order:

  1. 01

    Hire an architect or designer

    Agree in writing on what they will draw, how many design rounds are included, and whether they will visit during construction.

  2. 02

    Design

    Rough layouts first, then a chosen scheme, then detailed drawings and selections.

  3. 03

    Permit set and engineering

    The permit drawings, with a structural engineer's calculations where required.

  4. 04

    Bids

    Washington's Department of Labor & Industries (L&I) advises getting at least three written bids and comparing them carefully. Identical drawings make that comparison fair.

  5. 05

    Construction

    You sign with the contractor you choose. If the architect's contract includes it, the architect visits and reviews the work.

The strength is independence: the designer works for you, and price differences between bids show plainly. The weakness is that nobody prices the project until the drawings are done, so a design that bids over budget goes back for changes. A middle route, which Washington's public owners call general contractor/construction manager, brings a builder in during design to price it as it develops; ask your architect whether they work that way.

Do you need an architect to remodel a house in Washington?

Not by law, for a house. Washington's architect licensing law exempts design work and construction documents for "a residential building of up to and including four dwelling units," whatever its size (RCW 18.08.410). The Seattle Department of Construction and Inspections (SDCI) says house drawings "rarely require a professional stamp" and that you may prepare them yourself or hire a professional.

An engineer is a different matter. On Seattle's subject-to-field-inspection (STFI) permit, the city's quicker permit for small projects, a new beam or header in a bearing wall can be built without an engineer's stamp only up to 8 feet long under two stories and a roof, or 14 feet under one story and a roof. Longer spans need plans stamped by a civil or structural engineer, and the inspector may require stamped engineering for joists or rafters that go past the code's span tables (SDCI Tip 316, updated October 29, 2026).

Two more cases bring in a professional. On a steep slope, a slide area or other listed critical areas, SDCI requires a geotechnical report for exterior or foundation work. And a remodel that replaces wall surfaces in more than 60 percent of the house is likely a substantial alteration, which needs engineer-stamped seismic plans, approved Earthquake Home Retrofit plans or proof of a 1985 or later house to stay on the STFI permit. Beams are covered in opening a load-bearing wall.

When is hiring an architect first the better choice?

Architect first is often better when the design is the hard part, when a public board will review it, or when you want builders to compete on identical plans:

  • A designated landmark or a house in a historic district. Seattle has designated more than 400 landmarks and has eight historic districts, and a Certificate of Approval must be issued before changes are made to a landmark or to a property in one of those districts. In the Harvard-Belmont district it is required before any building permit for work visible from the street. A designer who has taken drawings before a review board helps.
  • A steep, slide-prone or liquefaction-prone lot. Exterior or foundation work there needs a geotechnical report, and Tip 316 says exterior work on a site with an environmentally critical area does not qualify for the STFI permit unless SDCI staff approve it.
  • A large addition, a second story or a new layout for most of the house. These go through full plan review, and the design choices drive most of the cost.
  • You want several bids on the same plans. If price competition matters most to you, finished drawings let L&I's advice to compare at least three written bids work as intended.
  • You want an adviser on your side during construction. An architect hired for construction visits works for you, not for the builder.
  • A long-range plan for the whole property, such as a house, an ADU and a garden built in phases over several years.

Design-build usually fits better when the project is a kitchen, bathrooms, a basement or an interior remodel of an existing house; when the budget is fixed and you want each design choice priced as you make it; and when the house is old enough that what is behind the walls will shape the design.

How do design fees and drawings work on each path?

Each firm sets its own terms, so ask about money and ownership before any design starts and get the answers in writing.

  • What does the design phase cost, and is it a fixed fee, an hourly rate or part of the construction price?
  • If I stop after design, what do I owe, and do I get the drawings?
  • Who owns the drawings, and may another contractor build from them?
  • Does the design include permit drawings, energy code forms and the structural engineer, or are those extra?
  • How many rounds of changes are included?
  • On the architect path: are site visits during construction included, and how many?
  • On the design-build path: when will the firm give a construction price, and how firm is it?

Read the written estimate the same way on both paths: what is included, what is an allowance and what is left out. The estimate guide shows what to look for.

What should you check whichever path you choose?

The same state checks apply to every builder. A contractor must be registered with L&I, post a $30,000 bond as a general contractor ($15,000 as a specialty contractor), and carry liability insurance of at least $200,000 for public liability plus $50,000 for property damage, or $250,000 combined. A city may not issue a permit for work by a contractor who must register without first checking that the registration is current (RCW 18.27.110).

An architect must hold a Washington license, which the Department of Licensing lets you look up. A residential designer who is not an architect may design a house under the exemption above, so judge that person on references and finished work.

Before work starts on a residential job of $1,000 or more, the contractor must give you the state's disclosure statement (RCW 18.27.114). The questions to ask a contractor cover the rest.

Giant Builders Seattle works as a design-build contractor. The checks in this article apply to it as much as to any firm, and its state registration is listed on the about page.