How much deposit can a Washington contractor ask for?

There is no fixed limit. Chapter 18.27 RCW, Washington's contractor registration law, does not set a maximum deposit, so the amount is whatever the contract says. L&I's hiring guide says to pay a reasonable down payment, tie anything beyond it to completed work, and be cautious of contractors who require large deposits or the full cost up front. In a 2008 consumer tip, the Attorney General's office suggested limiting the first payment to 10 to 20 percent, so the final amount can be held back based on performance.

A deposit usually covers what happens before construction: design time, permit preparation and the first orders. If a payment is meant to buy materials, L&I suggests asking that the check be made payable to both the contractor and the supplier. Get a receipt for every payment, and pay the business, not an individual: L&I warns about requests to pay in a person's name rather than the business name, and about contractors who insist on cash.

What does a sensible draw schedule for a remodel look like?

One where each payment follows a stage of work you can see. L&I advises paying when significant phases are completed, not because a calendar date has arrived, and withholding a portion until all the work is done and you are satisfied. It also warns against paying for work that is unfinished or has not passed inspection.

The schedule below is an example of that practice for a full kitchen remodel. It is not a legal standard, and the shares on a real contract depend on the job, especially on how much material must be ordered early.

Example draw schedule for a kitchen remodel (practice, not law)
PaymentWhen it is dueExample share
DepositAt signing, for design, permits and early orders10%
Draw 1Demolition done; rough framing, wiring and plumbing in place and inspected25%
Draw 2Insulation and drywall complete15%
Draw 3Cabinets set20%
Draw 4Counters, tile and fixtures installed20%
Final paymentFinal inspection passed, walkthrough list finished, lien releases received10%

Each payment also carries sales tax at the job site's rate. If the contract holds back retainage, the Department of Revenue says the tax is figured before the retainage is deducted.

What must a Washington contractor give you before work starts?

The disclosure statement in RCW 18.27.114. A contractor working on a home of up to four units, or the accessory structures on that property, under a contract of $1,000 or more must give the customer this Notice to Customer before starting work, and keep your signed copy for at least three years. L&I publishes a model statement. It tells you:

  • The contractor's registration number, the bond amount and the registration's expiration date.
  • That the bond might not be enough to cover a claim, and that it is shared with the contractor's other customers, suppliers, subcontractors and taxing authorities.
  • That you may withhold a contractually defined percentage of the contract as retainage, money held back for a stated period to make sure the work is completed.
  • That your property may be liened if a supplier, an employee or a subcontractor is not paid, and that you could pay twice for the same work.
  • That you may ask the contractor for original lien release documents from each supplier and subcontractor.

The notice protects you in two more ways. A contractor who did not give it cannot bring or keep a lien claim on that contract. And the contractor must tell you if its registration expires or is suspended or revoked before the job is finished. The estimate article lists the other papers to check.

How do construction liens work on a Washington home remodel?

A construction lien is a claim against your property for unpaid work or materials. Under chapter 60.04 RCW, anyone who furnishes labor, professional services, materials or equipment to improve real property at the owner's request has a lien right for what they are owed. The risk for a homeowner is paying the contractor in full and then facing a claim from someone the contractor did not pay.

For the repair, alteration or remodel of an existing single-family house you own and live in, the law gives you more protection than it gives the owner of a new building (RCW 60.04.031):

  • Anyone who contracts directly with you, such as your general contractor, needs to send no notice and has a lien for the full amount due under the contract.
  • A supplier or subcontractor that contracts with your contractor, not with you, must send you a written notice of the right to claim a lien, headed Notice to Owner.
  • That supplier's or subcontractor's lien can be paid only from the part of the contract price you had not yet paid your contractor when the notice was received, whether or not that amount was already due.
  • The notice form itself warns that laborers on the project may claim a lien without sending a notice.

So the day a Notice to Owner arrives matters. Note the date, what you have paid so far and who sent it. From then on, pay for that sender's share with a joint check, or get its lien release before you pay the contractor for that work. L&I's page on liens says to take any lien notice seriously and tell your contractor you received it.

How long does someone have to file a lien on my house?

Lien deadlines in chapter 60.04 RCW
StepDeadlineStatute
The claimant records a claim of lien with the countyWithin 90 days after it last furnished labor, services, materials or equipmentRCW 60.04.091
The claimant sends you a copy of the recorded claimWithin 14 days of recording, by certified or registered mail or personal serviceRCW 60.04.091
The claimant sues to enforce the lienWithin 8 calendar months after recording, with service on the owner within 90 days of filingRCW 60.04.141
The claimant releases its lien rights once paidImmediately, on payment and your demandRCW 60.04.071

If a claim is recorded and the claimant sues, you may withhold the amount of the claim from your contractor while the case is pending (RCW 60.04.151). If you or the contractor dispute the claim, either of you can record a surety bond that releases the property from the lien (RCW 60.04.161). A lawyer who handles construction liens can advise on a recorded claim.

What is a lien release, and when should you ask for one?

A lien release is a signed statement from a supplier or subcontractor that it has been paid and gives up its lien rights for that payment. Under RCW 60.04.071, a claimant who has been paid must prepare and deliver a release when the owner asks. L&I publishes a sample waiver of lien.

  • Ask for releases from the suppliers and subcontractors that sent you a Notice to Owner before you pay the contractor for their part.
  • Before the final payment, get signed releases from all major subcontractors and suppliers, as L&I advises.
  • Where a release is not yet in hand, pay with a joint check made out to the contractor and the supplier or subcontractor.
  • If you receive a notice of intent to lien, ask the contractor for that sender's lien release and hold further payments until it is resolved, as L&I advises.
  • Keep receipts for every payment and copies of every notice and release.

What protection do you have if the contractor does not finish?

Three kinds, none of them complete. The first is the contractor's bond: $30,000 for a general contractor and $15,000 for a specialty contractor, shared by every claimant. A homeowner suing on the bond for breach of contract must file within two years from the date the work was substantially completed or abandoned, whichever came first (RCW 18.27.040).

The second is the state's Homeowner Recovery Fund, created by RCW 18.27.410. If you own and live in a single-family home or a building of up to four units (not a condominium), win a final judgment ordered after July 1, 2026 against a registered contractor, and have first gone against the bond, you may apply within 90 days after the court case ends. Payments are up to $25,000 per contractor per parcel, as funds allow, with a waitlist when the account runs short.

The third is a performance bond, which you can ask for before work starts. L&I suggests considering one for projects over $6,000; it protects you for the project's full value and may carry a fee.

Paying in step with finished work keeps the amount at risk small, which matters more than any of the three. The contractor check article shows how to read a contractor's bond and insurance record before you sign. Giant Builders gives you one project manager as your point of contact and ends every job with a walkthrough.