ADU and DADU cost in Seattle

What a backyard cottage, a garage conversion or a basement apartment costs in Seattle in 2026, and the taxes, city fees and county charge that sit outside a builder's price.

By Giant Builders SeattleUpdated Rules checked against city sources in November 2026

WA contractor license
GIANTBS782RZ
UBI
604991679
Permits
Prepared and filed by us
Workmanship warranty
5 years
Estimate
Free, in your home, in writing

The short answer

A new backyard cottage in Seattle typically costs $250,000 to $500,000 before tax, a garage conversion $150,000 to $300,000 and a unit inside the house $120,000 to $250,000. On top of the contract come 10.55% sales tax, the city’s permit fees, and King County’s sewer capacity charge of $46.01 a month for 15 years.

Basic one-story ADU, Seattle (Cost vs. Value 2025)
$210,944
What that figure works out to over 660 sq ft
$320 per sq ft
King County sewer capacity charge, for 15 years
$46.01 a month
Seattle sales tax, charged on labor and materials
10.55%

By type

ADU cost by type of unit

An ADU is a second, smaller home on the same lot as a house. Where it goes decides most of the price. The ranges are typical for Seattle in 2026.

Typical Seattle ADU costs in 2026
TypeWhat the money buildsTypical range, before taxWith 10.55% sales taxTime on site
Unit inside the houseA basement or attached apartment (an AADU): the shell exists, so the money goes to a kitchen, a bathroom, an entrance, separation from the main house and bringing the space up to code.$120,000 to $250,000$132,700 to $276,4003 to 5 months
Garage conversionAn existing garage turned into a legal home: insulation, a floor over the slab, new plumbing and sewer, windows, heat, and often structural work on an old building.$150,000 to $300,000$165,800 to $331,7004 to 6 months
New backyard cottageA detached unit (a DADU) built from the ground up: site work, foundation, utilities trenched from the street or the house, and every finish new.$250,000 to $500,000$276,400 to $552,8006 to 9 months
Ranges are typical local pricing, checked against Remodeling magazine's 2025 Cost vs. Value figure and the ranges Seattle-area contractors published in 2026. They are not a quote.

The published figure, and why cottages here cost more

Remodeling magazine’s 2025 Cost vs. Value report prices an accessory dwelling unit in Seattle at $210,944, about 27% above its national average of $166,406. The unit it describes is simple: one story on a slab, 660 square feet, one bedroom, a bathroom with a walk-in shower, a small kitchen, a living room, a mini-split heat pump and a paved parking space.

Detached units built in Seattle usually cost more than that, and the ranges contractors here published in 2026 run from under $200,000 to well over $500,000. The reasons are on the lot, not in the finishes.

What moves a cottage toward the high end

  • Two stories. A small lot often leaves room only for a small footprint, so the unit goes up. Stairs, a second floor system and taller walls cost more per square foot than a slab and a roof.
  • Utilities. Sewer, water and power are trenched from the house or the street. A long run, a shared or failing side sewer, or a small electrical service adds cost before the unit starts.
  • Access and slope. If machines and materials reach the yard only through a side gate, or the yard slopes, the foundation and the labor both grow.
  • Size. Seattle allows up to 1,000 square feet, or 1,200 with three or more bedrooms. See the Seattle ADU rules.

Outside the contract

The costs that are not in a builder's price

Taxes, fees and charges on a Seattle ADU
LineAmount in 2026Who sets it
Sales tax10.55% of the whole contract, labor included. On $300,000 that is $31,650.Washington Dept. of Revenue and the city
Building permit and plan reviewSet from the value of the work: $5,452.65 at $200,000, $7,053.90 at $300,000, $8,628.90 at $400,000, technology fee included. About three quarters is due when the plans are submitted.Seattle SDCI
Hourly reviewsReviews such as drainage and soils are billed by the hour, at $292.Seattle SDCI
Electrical permit$55.48 plus $26.28 per circuit up to 25 amps and $146 for a service up to 125 amps ($292 for 150 to 200 amps), plus 5%.Seattle SDCI
Plumbing permit$137 plus $27 per fixture. A gas line needs its own permit at the same rate per outlet.Public Health Seattle & King County
Sewer capacity charge$46.01 a month for 15 years, billed every three months: $8,281.80 over the full term, less if paid off early.King County
New or larger electrical servicePriced by the utility for each site.Seattle City Light
Fees computed from the 2026 SDCI Fee Subtitle, the Public Health fee list and King County’s 2026 capacity charge rates.

What Seattle does not charge an ADU

The city’s ADU page says parking, street improvements and mandatory housing affordability contributions do not apply to accessory dwelling units. No off-street parking space has to be built.

How the city values the work

The permit fee follows the value the city assigns, not the price in your contract. The fee schedule says the department determines the value of construction itself and uses national building valuation data to do it. For a new cottage that value can come out below what the unit costs to build in Seattle, and then the fee is lower than the figures above. Treat them as estimates until the city has valued your plans.

A worked example

Adding it up for one backyard cottage

Worked example, not a real job

Example: an 800 sq ft, two-bedroom backyard cottage

A typical new detached unit on a flat lot with alley access, built from a custom plan. Priced at $400 per square foot, above the report's $320 because it is two stories with full utility connections. The fees are computed from the 2026 schedules.

LineHow it is worked outAmount
Construction contract800 sq ft at $400 per sq ft. Design, site work, foundation, structure, utilities from the house, finishes and cleanup.$320,000
Sales tax10.55% of the contract price (Seattle, October to December 2026).$33,760
Building permit and plan reviewFull plan review, if the city values the work at $320,000: permit fee $3,509, plan review fee $3,509, technology fee $350.90. Lower if the city's own valuation is lower.$7,368.90
Electrical permitSeattle's schedule: $55.48 administrative fee, a service up to 125 amps at $146, 12 circuits up to 25 amps at $26.28, two larger circuits at $43.80, plus 5%.$634.66
Plumbing permitPublic Health Seattle & King County: $137 plus $27 for each of 8 fixtures.$353
Total to build, with tax and permits$362,116.56
Typical numbers put together to show how the lines add up. This is not a project we built and not a quote. Not in the total: King County's capacity charge of $46.01 a month for 15 years ($8,281.80), hourly city reviews, Seattle City Light's charge for the electrical service, and any repair of the side sewer.

Budget your own ADU

The ADU cost calculator takes the type of unit, its size and your lot's conditions and returns a range with the sales tax and the capacity charge shown.

Open the ADU calculator

Questions

ADU and DADU cost questions, answered

01

How much does it cost to build a DADU in Seattle?

A new backyard cottage in Seattle typically costs $250,000 to $500,000 before tax, depending on its size, the slope and access of the yard and how far the utilities run. Converting an existing garage is typically $150,000 to $300,000 and a unit inside the house $120,000 to $250,000. Remodeling magazine's 2025 Cost vs. Value report prices a basic one-story, one-bedroom accessory dwelling unit in Seattle at $210,944. Add 10.55% sales tax on the whole contract.

02

How much does an ADU cost per square foot in Seattle?

The 2025 Cost vs. Value figure works out to about $320 per square foot for the 660 square foot unit the report describes. Custom cottages in Seattle usually run higher, because the report's unit is one story on a flat slab with basic finishes. A small unit costs more per square foot than a large one: the kitchen, the bathroom, the utility connections and the permits cost about the same at 400 square feet as at 1,000.

03

What is the least expensive kind of ADU to build?

Usually a unit inside the house, when there is a basement that is dry, tall enough and has a way to get its own entrance. The walls, the roof and the utilities are already there. A garage conversion comes next, if the garage is sound. A new cottage costs the most because everything is new, from the footing to the sewer connection.

04

What fees does Seattle charge to permit a DADU?

The building permit fee and the plan review fee are each set from the value the city assigns to the work. Under the 2026 fee schedule the two together, with the 5% technology fee, come to $5,452.65 at a value of $200,000, $7,053.90 at $300,000 and $8,628.90 at $400,000. Reviews such as drainage are billed by the hour on top, at $292. The electrical permit comes from the city and the plumbing permit from Public Health, at $137 plus $27 per fixture.

05

What is the King County sewer capacity charge for an ADU?

King County charges newly connected homes for sewage treatment capacity. An accessory dwelling unit, attached or detached, is billed 0.59 of a standard home. At the 2026 rate of $77.99 that is $46.01 a month, billed every three months for 15 years, about $8,280 in all, and the balance can be paid off early. Seattle reports every ADU permit to the county. The bill goes to the property owner and is not in a builder's price.

06

Do the city's pre-approved DADU plans save money?

They save design fees and time. Seattle keeps a gallery of pre-approved cottage designs, and the city says that in most cases a permit for one of them takes 2 to 6 weeks. The plans were drawn by local designers and architects and approved in advance, which is why the permit is quicker. They suit a flat, simple lot best.

07

How long does it take to build an ADU in Seattle?

About 6 to 9 months of construction for a new backyard cottage, 4 to 6 months for a garage conversion and 3 to 5 months for a unit inside the house. Design and the permit come first. A unit cannot use the city's quick field-inspection permit, so the plans go through full review unless a pre-approved plan is used.

08

Does an ADU pay for itself?

At resale alone, not fully: the 2025 Cost vs. Value report estimates that an accessory dwelling unit in Seattle returns 32.3% of its cost in sale price. Most owners build one for rent or for family, so the sum to do is rent or housing saved over the years you will own it, against the cost with tax, fees and the capacity charge included.

Free estimate

Find out what your lot can hold, and what it costs

We visit, look at the yard, the alley, the sewer and the electrical service, and tell you which kind of unit fits before you pay for drawings. Then we send a written, itemized estimate.